MSHA Team Meeting
11/15/2006
10:15 a.m. to 11: 28 a.m.
Attendees:
Joseph Breighner
Allison Czapracki
LaTanger Gray
Rashmi Jain
Abigail Jones
Dr. Nada Dabbagh
Items Discussed:
Meeting with Dr. Dabbagh
Reviewed the photos from the
Dr. Dabbagh gave feedback on the one-on-one meetings with her on 11/14
- Next semester she will be more proactive with meetings to present status report
- She will try to review minutes more closely; make suggestions if needed
- She will send an agenda of things she wants to discuss with us before hand so we have time to formulate responses
-
Colorado DVD
-
Allison and Rashmi compiling clips we feel we will use
-
Client wants to see more graphics, maps
-
Wants an example of audio in at least one of the scenarios
-
Let experts know if they want more complex questions, they need to write them
Will contact Sharon Cook if needed; still no response from Mike Hlavsa
Abi is verifying her scenario content with Mike Adkins with the WV Extension Office
-
is revising the JTA view
-
the HTML view is now called “Online” view
-
Reviewed structure of JTA content
-
Include an overall objective for each duty
-
One generic objective for all JTAs
-
-
If we don’t get what we need from MSHA re: Workforce Connections, we can construct a workaround.
Client Presentation
- Considering 12-7 or 12-8 for presentation; Nada will check client availability
- Important deliverable is the presentation
- The design treatment can be mailed to them the following week
Timeline
- Will need to work possibly Mondays and Fridays to meet critical project deadlines
- Allison prepared a working schedule for the next 6 days
-
We have the option of presenting 732 project on 12-8 or 12-12
Tomorrow
-
Joe and Abi will meet Dr. D at MSHA headquarters
-
The rest of us will meet at Commerce I to work
508 Conference Update (attended by Allison)
-
lots of disabled people in attendance
-
lots of vendors there
-
things to remember
-
difficult to make PDFs accessible; CommonLook a software used to make PDFs more accessible
-
508 Compliant is somewhat of a misnomer; agencies comply, products conform
-
"webtronic" content - Word docs, etc.that may or may not be 508 compliant
-
Dr. D will meet with us next Tuesday
11:30 –
(w/o Dr. D.)
Team Meeting
Team work schedule for the next six days
-
Allison, Tangie and Rashmi will arrive by 9:00 am on Thursday
-
Entire team will arrive on Friday by 9:00 am
-
Debrief from MSHA meeting
-
-
Entire team will arrive at 12 noon next Monday – 11-20
JTAs
- will need to point out that we are not linking EUS to 30 CFR
- Use the term “Learning Outcomes” for objectives